Once a soil erosion permit has been issued, site maintenance inspections are performed until projects are permanently stabilized and a Certificate of Completion has been granted by the Soil Erosion and Sedimentation Control Program.
Site Inspection Schedule
Permit Type
| Description
|
---|
Residential Permits
| At minimum inspection will occur on a bimonthly basis, throughout the duration of the permit. Residential Permit are valid for 18 months from the date of issuance, extensions are available |
Commercial Permits
| At minimum Inspections will occur on a monthly basis, throughout the duration of the permit. Commercial Permits are valid for 24 months from the date of issuance, extensions are available |
At a minimum, the Program will conduct inspections as mentioned above. The site inspection schedule does not include transfer inspections, re-inspections, final inspections or enforcement.